|
Central Nevada Test Area
and Project Shoal site Area
The Central Nevada Test Area and Project Shoal site are administered by the
Nevada Operations Office. The Central Nevada Test Area is located in south central
Nevada, 96 kilometers (60 miles) northeast of the City of Tonopah. The Project
Shoal Site is located 48 kilometers (30 miles) southeast of Fallon, Nevada.
The Department of Energy (DOE) used
this site for one subsurface nuclear test, Project Faultless, detonated in January
1968. The DOE conducted the test to determine the suitability of the area for
additional testing. It also conducted nonnuclear special experiments top determine
the behavior of seismic waves. The Central Nevada Test Area is no longer in
use. The land surface has been released for unrestricted use while subsurface
intrusion restrictions are still in effect.
The Central Nevada Test Area includes
radioactive contamination of the deep bedrock around the shot cavity and hazardous
waste contamination from the closed mud pits near the surface. Ground water
is the most likely transport medium for the deep contamination; however, because
of the depth of the contamination (in excess of 976 meters [3,200 feet]) and
the remoteness of the site, exposure to humans is unlikely. The DOE decommisioned
the site in 1973.
Project Shoal is approximately 30
miles southeast of Fallon. The DOE conducted a nuclear test at the site in October
1963. The purpose of the test was to determine the effect of a nuclear detonation
in a granite rock formation and to compare the seismic activity of natural earthquakes
with activity from an underground nuclear explosion. A 12-kiloton device was
detonated at a depth of 369 meters (1,211 feet). The test was conducted to improve
the ability to detect underground nuclear explosions.
At the Project Shoal site, contamination
consists of radioactive contamination of the deep granite bedrock and ground
water around the shot cavity and in the access drift for the device emplacement.
Ground water is the most likely transport medium for the deep contamination;
however, because of the depth of the contamination (in excess of 402 meters
[1,320 feet]) exposure to humans of the environment from this material is unlikely.
The DOE has not confirmed the existence of surface contamination from the abandoned
mud pit. Contaminated soil and drill cuttings are reported to have been mixed
with clean fill and buried onsite, but the DOW has not confirmed this report.
This estimate assumes the DOE will
maintain control of these sites. A definitive future use plan is not complete.
However, this report assumes the surface of these sites will be cleaned to a
level that permits Open Space use. The subsurface of the sites will be maintained
by the DEO as a Controlled Access area. The final future-use designation for
these sites will be determined by negotiations between the DOE and the State
of Nevada.
The environmental restoration strategy
will be to characterise ground water flow and areas of contamination, assess
risk, and model contaminant movement away from the shot cavities. The focus
will be on tritium, since it is the most mobile of the potential radiological
contaminants. The DOE will make maximum use of the existing data, including
monitoring data collected from the Long-Term Hydrolic Monitoring program well
networks at each area. The Long-Term Hydrolic Monitoring program sampling has
been completed annually at Project Shoal and the Central Nevada Test Area since
1972. The Department of Energy and the State of Nevada are currently preparing
a Federal Facilities Agreement to govern future activites at these sites.
Assessment activites provide for
the evaluation of data collected at the Central Nevada Test Area and the Project
Shoal site. Assessment activites at the Central Nevada Test Area and the Prohject
Shoal site will be conducted in accordance with the Federal Facility Agreement
and Consent Order. Activities at these sites are assumed to consist of characterising
the ground-water flow using existing monitoring well and characterising the
surface areas using additional field samples and tests. These activities will
provide information for generating a risk assessment for each site. Assessment
activities at Shoal are assumed to begin in FY 1996. Assessment activities at
the Central Nevada Test area are not scheduled to begin until FY 2002.
Waste is due to subsurface nuclear
detonations in and around the shot cavities. Until characterisation activites
are completed, remediation activities cannot be completely defined.
Surface contamination at the Central
Nevada Test Area consists of surface mud pits at the UC-1 and UC-4 areas that
contain drilling mud contaminated with medals and diesel fuel. A risk assessment
will be conducted to determine the best method for dealing with the mud pits.
Low-level and other waste in and around the subsurface shot cavities will not
be removed. Surface waste, assumed to comprise approximately 3,850 cubic meters
(5,044 cubic yards) of contaminated soil (hazardous waste) will be shipped to
an appropriate commercial disposal facility for disposal.
This estimate assumes the shaft at
the Shoal Test Area will be sealed. Negotiations are currently under way with
the State to determine the best method for dealing with the shaft. Surface contamination
at Project Shoal consists of a mud pit in which contaminated soil and cuttings
from the post-shot drilling were mixed with clean soil and buried. This estimate
assumes the contamination is below regulatory levels of concern and no removal
actions will be required. If the areas of potential contamination are not adequately
bounded by the present Long-Term Hydrologic Monitoring program networks, or
if there are potential exposure pathways not presently monitored, remedial actions
may include adding more monitoring wells to the existing network, placing use
restrictions on the ground water, excavating surface mud pits, and sealing and
abandoning the Shoal shaft.
The Environmental Protection Agency
(EPA) is monitoring the Project Shoal site and the Central Nevada Test Area
as part of the Long-Term Hydrologic Monitoring program. Monitoring consists
of sampling selected ground-water and surface-water collection locations around
each site. Sampling requires approximately one week per year per site, plus
the analysis of approximately 20 samples per site per year. Modifications to
the Long-Term Hydrologic Monitoring program networks and ground-water use restrictions
will be documented in a Corrective Action Decision Document. This report assumes
assessment and remedial action effort costs will continue to pay for this program.
Environmental Management program
costs at the Central Nevada Test Area and Project Shoal site are limited to
Environmental Restoration program assessment, remediation, and surveillance
and monitoring costs. Both the 1995 and change the cost assumptions regarding
needed remedial action. The 1996 life-cycle cost estimate are based on characterization
activites that are not complete and which, upon completion, could change the
cost assumption regarding needed remedial action. The 1996 life-cycle cost estimate
for the two sites $8.2 million. This is about $10 million less than the 1995
estimate for the entire Central Nevada Test Area. However, the 1995 estimate
including the Tonopah Test Range activities. The DOE has since transferred Tonopah
Test Range activities to the Nevada Test Site, Industrial Sites Category. This
change accounts for most of the $10 million reduction in the 1996 estimated
life-cycle cost.
|